DOT Garage Renovation
Back to Projects
COMPLETED PROJECT

Plumbing Renovation

NYC Department of Transportation

Modernized plumbing systems with water-saving fixtures

Completed: May 2023

Project Overview

This comprehensive renovation project for the NYC Department of Transportation's garage facility involved modernizing outdated plumbing systems with water-efficient fixtures and infrastructure. The project aimed to reduce water consumption, improve operational efficiency, and ensure compliance with the latest NYC building codes and sustainability standards.

Project Value

$1.2 Million

Duration

3 months

Efficiency Improvement

32% reduction in water usage

Compliance

Meets NYC Local Law 152 and DOB requirements

Scope of Work

  • Complete replacement of outdated plumbing fixtures with water-efficient models
  • Installation of new copper piping throughout the facility
  • Implementation of smart water management systems for usage monitoring
  • Upgrade of drainage systems to improve flow and prevent backups
  • Installation of water-saving technologies in all restrooms and utility areas
  • Comprehensive testing and certification of all installed systems

Project Timeline

Phase 1

Initial Assessment

February 2023

Comprehensive evaluation of existing plumbing systems and infrastructure needs.

2
Phase 2

Design & Planning

March 2023

Development of detailed renovation plans and procurement of materials.

3
Phase 3

Implementation

March-April 2023

Installation of new fixtures, piping systems, and water-saving technologies.

4
Phase 4

Testing & Handover

May 2023

Rigorous testing, final inspections, and project completion.

Challenges & Solutions

Working in an Active Facility

The DOT garage needed to remain operational throughout the renovation, presenting significant logistical challenges.

Our Solution:

We implemented a phased approach, working in sections during off-peak hours and weekends. Our team coordinated closely with facility management to ensure minimal disruption to daily operations while maintaining the highest safety standards.

Aging Infrastructure Complications

The existing plumbing system was significantly outdated, with undocumented modifications and unexpected layout issues.

Our Solution:

Our experienced team conducted thorough preliminary investigations and created detailed as-built drawings before beginning work. We maintained flexibility in our approach, quickly adapting to unforeseen conditions while keeping the project on schedule.

Project Gallery

DOT Garage Renovation - Before

Original plumbing infrastructure before renovation

DOT Garage Renovation - During

Installation of new water-efficient fixtures

DOT Garage Renovation - After

Completed renovation with modern plumbing systems

Client Testimonial

"
HEPCO's team demonstrated exceptional professionalism throughout the renovation project. They navigated the challenges of working in our active facility with minimal disruption, and the water savings we've achieved have exceeded our expectations. The project was completed on time and within budget.
"

Michael Rodriguez

Facilities Manager, NYC Department of Transportation

Key Results

32%

Reduction in water usage

$45K

Annual utility cost savings

100%

Code compliance achieved

Additional Outcomes:

  • Improved water pressure and system reliability throughout the facility
  • Enhanced maintenance accessibility for future servicing
  • Comprehensive documentation and training for facility staff
  • Project completed on schedule and within budget constraints

Technical Specifications

ComponentSpecification
Fixture TypeLow-flow water fixtures
Piping MaterialCopper with lead-free solder
Control SystemsSmart water management system
ComplianceNYC Plumbing Code & Green Building Standards